In my previous blog post, we covered the basics of what an electric vehicle (EV) is and how they work. I discussed some of the benefits of owning an EV and answered a few questions from readers. This week, let's take a closer look at one of the most popular types of EVs on the market today: plug-in hybrids (PHEVs). As you may know, PHEVs are a type of hybrid vehicle that can be plugged into an electrical outlet to recharge the battery. When the battery is fully charged, the PHEV can be driven like a regular electric car. However, if the battery runs low, the PHEV can also run on gasoline like a regular hybrid car. This makes them a great option for people who want to get all of the benefits of owning an EV but are worried about being able to drive in areas where there isn't a good charging infrastructure. So far, Tesla has been the only company to release a mass-market PHEV, but more companies are expected to enter this market in coming years. In this blog post, I'll discuss som
Question | Answer |
---|---|
Form Name | Form Eps 11 |
Form Length | 1 pages |
Fillable? | No |
Fillable fields | 0 |
Avg. time to fill out | 15 sec |
Other names | eps 11 subject name, Designation, Sluice, EPS |
|
|
|
|
|
|
FORM EPS 11 |
|
|
SYABAS DISTRICT : …………………………………………….. |
||||||
|
FINAL JOINT INSPECTION REPORT (EXTERNAL PIPELINE) |
|
|
||||
|
( Valid for six (6) months prior taking over date ) |
|
|
||||
Name of Development |
: _____________________________________ |
||||||
File No. |
: _____________________________________ |
||||||
Approved Plan No. |
: _____________________________________ |
||||||
(Attach approved plan and |
|
|
|
|
|
||
Date of Site Visit |
: _____________________________________ |
||||||
Phase / Name of location pipeline checked |
: _____________________________________ |
||||||
|
Work Description |
|
|
|
|
Remarks |
|
A) PIPELINES |
|
|
|
Satisfactory |
Unsatisfactory |
Comments |
|
|
|
|
|
|
(tick relevant |
Column) |
|
|
|
Type of |
Diameter |
Length |
|
|
|
|
|
pipe |
(mm) |
(m) |
|
|
|
1) |
Main Pipes |
|
|
|
|
|
|
2) |
Communication Pipes |
|
|
|
|
|
|
|
|
Type |
Nos |
Size(mm) |
|
|
|
3) |
Sluice Valves |
|
|
|
|
|
|
4) |
Butterfly Valves |
|
|
|
|
|
|
5) |
Scour Valves |
|
|
|
|
|
|
6) |
Air Valve |
|
|
|
|
|
|
7) |
Hydrants |
|
|
|
|
|
|
8) |
Valve Chambers |
|
|
|
|
|
|
9) |
Pipe Markers |
|
|
|
|
|
|
10) |
Pressure reducing valves |
|
|
|
|
|
|
11) |
Sampling Points |
|
|
|
|
|
|
12) |
Zone Meters |
|
|
|
|
|
|
13) |
Bulk meter with proper meter stand/filter |
|
|
|
|
|
|
|
/ gate valves |
|
|
|
|
|
|
14) |
Constant flow valve |
|
|
|
|
|
|
15) |
Over crossing with/without supports / |
|
|
|
|
|
|
|
Spike guards |
|
|
|
|
|
|
16) |
Other items : |
|
|
|
|
|
|
General Comments
Work done Satisfactory and acceptable to be taken over.
Work done Unsatisfactory for those items commented and need to be rectified and another inspection date to be arranged. Others (Please specify)
Remarks :
Jointly Inspected by : Head of Planning/Development Section SYABAS |
Jointly Inspected by : Technical Manager |
||
Signature |
: _________________________ |
Signature |
: _______________________ |
Name |
: _________________________ |
Name |
: _______________________ |
Date |
: _________________________ |
Date |
: _______________________ |
|
|
||
Jointly Inspected by : Head Of District (HOD) |
Jointly Inspected by : Secretary Of Work (SOW) |
||
Signature |
: _________________________ |
Signature |
: _______________________ |
Name |
: _________________________ |
Name |
: _______________________ |
Designation |
: _________________________ |
Designation |
: _______________________ |
Date |
: _________________________ |
Date |
: _______________________ |
|
|
||
Acknowledged by Consultant :______________________ |
Acknowledged by Developer :________________ |
||
Signature |
: _________________________ |
Signature |
: _______________________ |
Name |
: _________________________ |
Name |
: _______________________ |
Designation |
: _________________________ |
Designation |
: _______________________ |
Date |
: _________________________ |
Date |
: _______________________ |