Ac 150 5370 2F Form PDF Details

The AC 150 5370 2F form is a document used by the United States Air Force to request authorization for an activity. The form must be completed in full and submitted to the appropriate authority for approval. The AC 150 5370 2F form is used to request authorization for items such as construction projects, transportation of hazardous materials, and airfield operations. Completing the form accurately and submitting it on time is critical for ensuring that your activity proceeds without issue.

QuestionAnswer
Form NameAc 150 5370 2F Form
Form Length58 pages
Fillable?No
Fillable fields0
Avg. time to fill out14 min 30 sec
Other namesfaa advisory circular 150 5370 2g, faa ac 150 5370 2e, faa spcd, faa circular

Form Preview Example

U.S. Department of Transportation

Federal Aviation Administration

Advisory Circular

Subject: Operational Safety on

Date: 9/29/11

AC No: 150/5370-2F

Airports During Construction

Initiated by: AAS-100

 

1.Purpose. This AC sets forth guidelines for operational safety on airports during construction.

2.What this AC Cancels. This AC cancels AC 150/5370-2E, Operational Safety on Airports During Construction, dated January 17, 2003.

3.Whom This AC Affects. This AC assists airport operators in complying with Title 14 Code of Federal Regulations (CFR) Part 139, Certification of Airports (Part 139). For those certificated airports, this AC provides one way, but not the only way, of meeting those requirements. The use of this AC is

mandatory for those airport construction projects receiving funds under the Airport Improvement Program (AIP) or the Passenger Facility Charge (PFC) Program. See Grant Assurance No. 34, “Policies, Standards, and Specifications,” and PFC Assurance No. 9, “Standard and Specifications.” While we do

not require non-certificated airports without grant agreements to adhere to these guidelines, we recommend that they do so to help these airports maintain operational safety during construction.

4.Principal Changes.

a.Construction activities are prohibited in safety areas while the associated runway or taxiway is open to aircraft.

b.Guidance is provided in incorporating Safety Risk Management.

c.Recommended checklists are provided for writing Construction Safety and Phasing Plans and for daily inspections.

5.Reading Material Related to this AC. Numerous ACs are referenced in the text of this AC. These references do not include a revision letter, as they are to be read as referring to the latest version. Appendix 1 contains a list of reading material on airport construction, design, and potential safety hazards during construction, as well as instructions for obtaining these documents.

Michael J. O’Donnell

Director of Airport Safety and Standards

AC 150/5370-2F

September 29, 2011

 

 

Intentionally Left Blank

ii

September 29, 2011AC 150/5370-2F

Table of Contents

Chapter 1.

Planning an Airfield Construction Project

1

101.

Overview.

1

102.

Plan for Safety.

1

103.

Develop a Construction Safety and Phasing Plan (CSPP).

2

104.

Who Is Responsible for Safety During Construction?

3

Chapter 2.

Construction Safety and Phasing Plans

7

201.

Overview.

7

202.

Assume Responsibility.

7

203.

Submit the CSPP.

7

204.

Meet CSPP Requirements.

7

205.

Coordination.

11

206.

Phasing.

11

207.

Areas and Operations Affected by Construction Activity.

12

208.

Navigation Aid (NAVAID) Protection.

13

209.

Contractor Access.

13

210.

Wildlife Management.

15

211.

Foreign Object Debris (FOD) Management.

16

212.

Hazardous Materials (HAZMAT) Management.

16

213.

Notification of Construction Activities.

16

214.

Inspection Requirements.

17

215.

Underground Utilities.

17

216.

Penalties.

17

217.

Special Conditions.

17

218.

Runway and Taxiway Visual Aids.

18

219.

Marking and Signs for Access Routes.

24

220.

Hazard Marking, Lighting and Signing.

24

221.

Protection of Runway and Taxiway Safety Areas.

26

222.

Other Limitations on Construction.

28

Chapter 3.

Guidelines for Writing a CSPP

31

301.

General Requirements.

31

302.

Applicability of Subjects.

31

303.

Graphical Representations.

31

304.

Reference Documents.

31

305.

Restrictions.

31

306.

Coordination.

31

307.

Phasing.

32

308.

Areas and Operations Affected By Construction.

32

309.

Navigation Aid (NAVAID) Protection.

33

310.

Contractor Access.

33

311.

Wildlife Management.

34

312.

Foreign Object Debris (FOD) Management.

34

313.

Hazardous Materials (HAZMAT) Management.

34

314.

Notification of Construction Activities.

35

315.

Inspection Requirements.

35

316.

Underground Utilities.

35

317.

Penalties.

35

318.

Special Conditions.

35

319.

Runway and Taxiway Visual Aids.

35

320.

Marking and Signs for Access Routes.

36

321.

Hazard Marking and Lighting.

36

322.

Protection of Runway and Taxiway Safety Areas.

36

323.

Other Limitations on Construction.

36

Appendix 1.

Related Reading Material

37

iii

AC 150/5370-2F

September 29, 2011

Appendix 2.

Definition of Terms

39

Appendix 3.

Safety and Phasing Plan Checklist

43

Appendix 4.

Construction Project Daily Safety Inspection Checklist

51

 

 

List of Tables

 

Table 3-1 Sample Operations Effects

32

 

 

List of Figures

 

Figure 2-1 Markings for a Temporarily Closed Runway

19

Figure 2-2 Taxiway Closure

20

Figure 2-3

Lighted X in Daytime

22

Figure 2-4

Lighted X at Night

22

Figure 2-5 Interlocking Barricades

25

Figure 2-6

Low Profile Barricades

25

iv

September 29, 2011

AC 150/5370-2F

 

 

Chapter 1. Planning an Airfield Construction Project

101.Overview. Airports are complex environments, and procedures and conditions associated with construction activities often affect aircraft operations and can jeopardize operational safety. Safety considerations are paramount and may make operational impacts unavoidable. However, careful planning,

scheduling, and coordination of construction activities can minimize disruption of normal aircraft operations and avoid situations that compromise the airport’s operational safety. The airport operator

must understand how construction activities and aircraft operations affect one another to be able to develop an effective plan to complete the project. While the guidance in this AC is primarily used for construction operations, some of the concepts, methods and procedures described may also enhance the day-to-day airport maintenance operations, such as lighting maintenance and snow removal operations.

102.Plan for Safety. Safety, maintaining aircraft operations, and construction costs are all

interrelated. Since safety must not be compromised, the airport operator must strike a balance between maintaining aircraft operations and construction costs. This balance will vary widely depending on the operational needs and resources of the airport and will require early coordination with airport users and the FAA. As the project design progresses, the necessary construction locations, activities, and associated costs will be identified. As they are identified, their impact to airport operations must be assessed. Adjustments are made to the proposed construction activities, often by phasing the project, and/or to airport operations in order to maintain operational safety. This planning effort will ultimately result in a project Construction Safety and Phasing Plan (CSPP). The development of the CSPP takes place through the following five steps:

a.Identify Affected Areas. The airport operator must determine the geographic areas on the airport affected by the construction project. Some, such as a runway extension, will be defined by the project. Others may be variable, such as the location of haul routes and material stockpiles.

b.Describe Current Operations. Identify the normal airport operations in each affected area for each phase of the project. This becomes the baseline from which the impact on operations by construction activities can be measured. This should include a narrative of the typical users and aircraft operating within the affected areas. It should also include information related to airport operations: the Aircraft

Reference Code (ACRC) for each runway; Airplane Design Group (ADG) and Taxiway Design Group (TDG)1 for each affected taxiway; designated approach visibility minimums; available approach and departure procedures; most demanding aircraft; declared distances; available air traffic control services; airport Surface Movement Guidance and Control System plan; and others. The applicable seasons, days and times for certain operations should also be identified as applicable.

c.Allow for Temporary Changes to Operations. To the extent practical, current airport operations should be maintained during the construction. In consultation with airport users, Aircraft

Rescue and Fire Fighting (ARFF) personnel, and FAA Air Traffic Organization (ATO) personnel, the airport operator should identify and prioritize the airport’s most important operations. The construction

activities should be planned, through project phasing if necessary, to safely accommodate these operations. When the construction activities cannot be adjusted to safely maintain current operations, regardless of their importance, then the operations must be revised accordingly. Allowable changes include temporary revisions to approach procedures, restricting certain aircraft to specific runways and taxiways, suspension of certain operations, decreased weights for some aircraft due to shortened runways,

1Taxiway Design Group will be introduced in AC 150/5300-13A.

1

Chapter 1 Planning an Airfield Construction Project

AC 150/5370-2F

September 29, 2011

 

 

and other changes. An example of a table showing temporary operations versus current operations is shown in Table 3-1 Sample Operations Effects.

d.Take Required Measures to Revised Operations. Once the level and type of aircraft operations to be maintained are identified, the airport operator must determine the measures required to safely conduct the planned operations during the construction. These measures will result in associated costs, which can be broadly interpreted to include not only direct construction costs, but also loss of revenue from impacted operations. Analysis of costs may indicate a need to reevaluate allowable changes to operations. As aircraft operations and allowable changes will vary so widely among airports, this AC presents general guidance on those subjects.

e.Manage Safety Risk. Certain airport projects may require the airport operator to provide a Project Proposal Summary to help the FAA to determine the appropriate level of Safety Risk Management (SRM) documentation. The airport operator must coordinate with the appropriate FAA Airports Regional or District Office early in the development of the CSPP to determine the need for SRM documentation. See FAA Order 5200.11, FAA Airports (ARP) Safety Management System (SMS), for more information. If the FAA requires SRM documentation, the airport operator must at a minimum:

(1)Notify the appropriate FAA Airports Regional or District Office during the project

“scope development” phase of any project requiring a CSPP.

(2)Provide documents identified by the FAA as necessary to conduct SRM.

(3)Participate in the SRM process for airport projects.

(4)Provide a representative to participate on the SRM panel.

(5)Ensure that all applicable SRM identified risks elements are recorded and mitigated within the CSPP.

103.Develop a Construction Safety and Phasing Plan (CSPP). Development of an effective CSPP will require familiarity with many other documents referenced throughout this AC. See Appendix 1, Related Reading Material for a list of related reading material.

a.List Requirements. A CSPP must be developed for each on-airfield construction project funded by the Airport Improvement Program (AIP) or the Passenger Facility Charge (PFC) program or located on an airport certificated under Part 139. As per Order 5200.11, such projects do not include construction, rehabilitation, or change of any facility that is entirely outside the air operations area, does not involve any expansion of the facility envelope and does not involve construction equipment, haul routes or placement of material in locations that require access to the air operations area, increase the facility

envelope, or impact line-of-sight. Such facilities may include passenger terminals and parking or other

structures. However, extraordinary circumstances may trigger the need for a Safety Assessment and a CSPP. The CSPP is subject to subsequent review and approval under the FAA’s Safety Risk Management

procedures (see paragraph 102.e above). Additional information may be found in Order 5200.11.

b.Prepare a Safety Plan Compliance Document. The Safety Plan Compliance Document (SPCD)

details how the contractor will comply with the CSPP. Also, it will not be possible to determine all safety plan details (for example specific hazard equipment and lighting, contractor’s points of contact,

construction equipment heights) during the development of the CSPP. The successful contractor must define such details by preparing an SPCD that the airport operator reviews for approval prior to issuance of a notice-to-proceed. The SPCD is a subset of the CSPP, similar to how a shop drawing review is a subset to the technical specifications.

Chapter 1 Planning an Airfield Construction Project

2

September 29, 2011

AC 150/5370-2F

 

 

c.Assume Responsibility for the CSPP. The airport operator is responsible for establishing and enforcing the CSPP. The airport operator may use the services of an engineering consultant to help develop the CSPP. However, writing the CSPP cannot be delegated to the construction contractor. Only those details the airport operator determines cannot be addressed before contract award are developed by the contractor and submitted for approval as the SPCD. The SPCD does not restate nor propose differences to provisions already addressed in the CSPP.

104.Who Is Responsible for Safety During Construction?

a.Establish a Safety Culture. Everyone has a role in operational safety on airports during construction: the airport operator, the airport’s consultants, the construction contractor and subcontractors, airport users, airport tenants, ARFF personnel, Air Traffic personnel, including Technical Operations personnel, FAA Airports Division personnel, and others. Close communication and coordination between all affected parties is the key to maintaining safe operations. Such communication and coordination should start at the project scoping meeting and continue through the completion of the project. The airport operator and contractor should conduct onsite safety inspections throughout the project and immediately remedy any deficiencies, whether caused by negligence, oversight, or project scope change.

b.Assess Airport Operator’s Responsibilities. An airport operator has overall responsibility for all activities on an airport, including construction. This includes the predesign, design, preconstruction, construction, and inspection phases. Additional information on the responsibilities listed below can be found throughout this AC. The airport operator must:

(1)Develop a CSPP that complies with the safety guidelines of Chapter 2, Construction Safety and Phasing Plans, and Chapter 3, Guidelines for Writing a CSPP. The airport operator may develop the CSPP internally or have a consultant develop the CSPP for approval by the airport operator. For tenant sponsored projects, approve a CSPP developed by the tenant or its consultant.

(2)Require, review and approve the SPCD by the contractor that indicates how it will comply with the CSPP and provides details that cannot be determined before contract award.

(3)Convene a preconstruction meeting with the construction contractor, consultant, airport employees and, if appropriate, tenant sponsor and other tenants to review and discuss project safety before beginning construction activity. The appropriate FAA representatives should be invited to attend

the meeting. See AC 150/5300-9, Predesign, Prebid, and Preconstruction Conferences for Airport Grant Projects. (Note “FAA” refers to the Airports Regional or District Office, the Air Traffic Organization, Flight Standards Service, and other offices that support airport operations, flight regulations, and construction/environmental policies.)

(4)Ensure contact information is accurate for each representative/point of contact identified in the CSPP and SPCD.

(5)Hold weekly or, if necessary, daily safety meetings with all affected parties to coordinate activities.

(6)Notify users, ARFF personnel, and FAA ATO personnel of construction and conditions that may adversely affect the operational safety of the airport via Notices to Airmen (NOTAM) and other methods, as appropriate. Convene a meeting for review and discussion if necessary.

(7)Ensure construction personnel know of any applicable airport procedures and of changes to those procedures that may affect their work.

(8)Ensure construction contractors and subcontractors undergo training required by the CSPP and SPCD.

3

Chapter 1 Planning an Airfield Construction Project

AC 150/5370-2F

September 29, 2011

 

 

(9)Ensure vehicle and pedestrian operations addressed in the CSPP and SPCD are coordinated with airport tenants, the airport traffic control tower (ATCT), and construction contractors.

(10)At certificated airports, ensure each CSPP and SPCD is consistent with Part 139.

(11)Conduct inspections sufficiently frequently to ensure construction contractors and tenants comply with the CSPP and SPCD and that there are no altered construction activities that could create potential safety hazards.

(12)Resolve safety deficiencies immediately. At airports subject to 49 CFR Part 1542, Airport Security, ensure construction access complies with the security requirements of that regulation.

(13)Notify appropriate parties when conditions exist that invoke provisions of the CSPP and SPCD (for example, implementation of low-visibility operations).

(14)Ensure prompt submittal of a Notice of Proposed Construction or Alteration (Form 7460-1) for conducting an aeronautical study of potential obstructions such as tall equipment (cranes, concrete pumps, other.), stock piles, and haul routes. A separate form may be filed for each potential obstruction, or one form may be filed describing the entire construction area and maximum equipment height. In the latter case, a separate form must be filed for any object beyond or higher than the originally evaluated area/height. The FAA encourages online submittal of forms for expediency. The appropriate FAA Airports Regional or District Office can provide assistance in determining which objects require an aeronautical study.

(15)Promptly notify the FAA Airports Regional or District Office of any proposed changes to the CSPP prior to implementation of the change. Changes to the CSPP require review and approval by the airport operator and the FAA. Coordinate with appropriate local and other federal government agencies, such as EPA, OSHA, TSA, and the state environmental agency.

c.Define Construction Contractor’s Responsibilities. The contractor is responsible for complying with the CSPP and SPCD. The contractor must:

(1)Submit a Safety Plan Compliance Document (SPCD) to the airport operator describing how it will comply with the requirements of the CSPP and supplying any details that could not be determined before contract award. The SPCD must include a certification statement by the contractor that indicates it understands the operational safety requirements of the CSPP and it asserts it will not deviate from the approved CSPP and SPCD unless written approval is granted by the airport operator. Any

construction practice proposed by the contractor that does not conform to the CSPP and SPCD may impact the airport’s operational safety and will require a revision to the CSPP and SPCD and re-

coordination with the airport operator and the FAA in advance.

(2)Have available at all times copies of the CSPP and SPCD for reference by the airport operator and its representatives, and by subcontractors and contractor employees.

(3)Ensure that construction personnel are familiar with safety procedures and regulations on the airport. Provide a point of contact who will coordinate an immediate response to correct any construction-related activity that may adversely affect the operational safety of the airport. Many projects will require 24-hour coverage.

(4)Identify in the SPCD the contractor’s on-site employees responsible for monitoring compliance with the CSPP and SPCD during construction. At least one of these employees must be on- site whenever active construction is taking place.

(5)Conduct inspections sufficiently frequently to ensure construction personnel comply with the CSPP and SPCD and that there are no altered construction activities that could create potential safety hazards.

Chapter 1 Planning an Airfield Construction Project

4

September 29, 2011

AC 150/5370-2F

 

 

(6)Restrict movement of construction vehicles and personnel to permitted construction areas by flagging, barricading, erecting temporary fencing, or providing escorts, as appropriate and as specified in the CSPP and SPCD.

(7)Ensure that no contractor employees, employees of subcontractors or suppliers, or other persons enter any part of the air operations area (AOA) from the construction site unless authorized.

(8)Ensure prompt submittal through the airport operator of Form 7460-1 for the purpose of conducting an aeronautical study of contractor equipment such as tall equipment (cranes, concrete pumps, other equipment), stock piles, and haul routes when different from cases previously filed by the airport operator. The FAA encourages online submittal of forms for expediency.

d.Define Tenant’s Responsibilities if planning construction activities on leased property. Airport tenants, such as airline operators, fixed base operators, and FAA ATO/Technical Operations sponsoring construction must:

(1)Develop, or have a consultant develop, a project specific CSPP and submit it to the airport operator for certification and subsequent approval by the FAA. The approved CSPP must be made part of any contract awarded by the tenant for construction work.

(2)In coordination with its contractor, develop an SPCD and submit it to the airport operator for approval to be issued prior to issuance of a Notice to Proceed.

(3)Ensure that construction personnel are familiar with safety procedures and regulations on the airport.

(4)Provide a point of contact of who will coordinate an immediate response to correct any construction-related activity that may adversely affect the operational safety of the airport.

(5)Identify in the SPCD the contractor’s on-site employees responsible for monitoring compliance with the CSPP and SPCD during construction. At least one of these employees must be on- site whenever active construction is taking place.

(6)Ensure that no tenant or contractor employees, employees of subcontractors or suppliers, or any other persons enter any part of the AOA from the construction site unless authorized.

(7)Restrict movement of construction vehicles to construction areas by flagging and barricading, erecting temporary fencing, or providing escorts, as appropriate, and as specified in the CSPP and SPCD.

(8)Ensure prompt submittal through the airport operator of Form 7460-1 for the purpose of conducting an aeronautical study of contractor equipment such as tall equipment (cranes, concrete pumps, other.), stock piles, and haul routes. The FAA encourages online submittal of forms for expediency.

5

Chapter 1 Planning an Airfield Construction Project

AC 150/5370-2F

September 29, 2011

 

 

Intentionally Left Blank

Chapter 1 Planning an Airfield Construction Project

6

How to Edit Ac 150 5370 2F Form Online for Free

faa circular can be filled out without difficulty. Just open FormsPal PDF editing tool to accomplish the job promptly. The editor is continually updated by us, receiving additional functions and growing to be much more versatile. Starting is easy! All you should do is stick to the following simple steps directly below:

Step 1: Access the PDF doc inside our tool by clicking on the "Get Form Button" at the top of this webpage.

Step 2: As soon as you access the file editor, you will find the form ready to be completed. Aside from filling out different blank fields, you could also perform other actions with the form, specifically writing any textual content, modifying the original text, adding illustrations or photos, affixing your signature to the document, and much more.

As a way to finalize this form, be sure to type in the necessary information in each and every area:

1. Whenever submitting the faa circular, be certain to complete all important blank fields in the associated area. This will help to facilitate the process, enabling your information to be processed efficiently and correctly.

airports during construction completion process described (step 1)

2. Your next stage would be to submit the next few fields: Meet CSPP Requirements , Foreign Object Debris FOD, Chapter , Guidelines for Writing a CSPP, General Requirements Applicability, Wildlife Management , Foreign Object Debris FOD, and Hazard Marking and Lighting.

airports during construction completion process outlined (part 2)

3. Throughout this part, examine Wildlife Management , Hazard Marking and Lighting, Appendix , Related Reading Material, and iii. All these are required to be filled in with highest accuracy.

airports during construction completion process outlined (part 3)

It is easy to make an error when completing your Wildlife Management , consequently ensure that you look again before you'll finalize the form.

4. To move onward, this part involves filling out a handful of form blanks. Examples include AC F, September , Appendix Appendix Appendix , Definition of Terms Safety and, Table Sample Operations Effects , List of Tables, List of Figures, Figure Markings for a Temporarily, Figure Taxiway Closure , Figure Lighted X in Daytime , Figure Lighted X at Night , Figure Interlocking Barricades , and Figure Low Profile Barricades , which you'll find essential to moving forward with this particular form.

airports during construction writing process described (step 4)

5. To wrap up your form, this final section features several extra blank fields. Completing and other changes An example of a, d Take Required Measures to, to be maintained are identified, e Manage Safety Risk Certain, Project Proposal Summary to help, Notify the appropriate FAA, scope development phase of any, and Provide documents identified by is going to finalize everything and you will be done in a blink!

Learn how to complete airports during construction portion 5

Step 3: Spell-check all the details you've inserted in the form fields and then press the "Done" button. Get your faa circular the instant you sign up at FormsPal for a 7-day free trial. Conveniently use the form from your personal cabinet, with any edits and adjustments conveniently synced! FormsPal ensures your data confidentiality by using a protected method that in no way records or shares any sort of private data involved. Be assured knowing your files are kept safe each time you use our tools!