ARS 372 PDF Details

The ARS 372 form is a contractor payment request document issued under the authority of the USDA Agricultural Research Service (USDA ARS). Contractors working on ARS-managed construction and improvement projects use this form to formally document and request payment for work completed under the terms of their government contract.

Contents of the ARS 372 Document

The document is organized by type of financial entry and includes the following key sections:

The lower section of each page contains a certification signed by the contractor. This certification confirms that all payment amounts are valid under the contract and that all payments to subcontractors and suppliers are current or will be made from the funds received. The form also requires a concurrence signature from the Engineer Project Manager (EPM) or Contracting Officer's Representative (COR) before payment is processed.

Contractors who need a related document for the same project may also reference the ARS 371 form, which precedes the ARS 372 in the payment process, or the construction payment request form for construction-specific billing on other project types.

QuestionAnswer
Form NameArs 372
Form Length1 pages
Fillable?No
Fillable fields0
Avg. time to fill out15 sec
Other namesars372 form instructions, ars372, form ars 33 1008, ares download

How to Fill Out Form ARS-372

Form ARS-372 at a glance

What it is: Form ARS-372 (06/2011) is the CONTRACTOR'S REQUEST FOR PAYMENT TRANSMITTAL.

Who signs: Sign on SIGNATURE OF CONTRACTOR'S AUTHORIZED REPRESENTATIVE and enter the DATE SIGNED.

A filled-in Form ARS-372 example: a partial payment request

Form ARS-372 example filled out, example: a partial payment request
Jane Ann Sample requests a partial payment on Form ARS-372. Her contract was 100,000.00, a change order added 5,000.00, and her work to date is worth 60,000.00. The picture shows the filled form, and none of its entries is real. This is a partial payment, so FINAL PAYMENT stays empty. Retainage is 10 percent of the total value of work completed and stored material. Two lots of stored material are listed, so the other Description and Value rows stay empty. The signers have dated their lines.

How to fill out Form ARS-372, box by box

Contract no., Partial payment no., Project, Requisition no. and Location

Form ARS-372 example filled out, contract no., Partial payment no., Project, Requisition no. and Location

Fill in the CONTRACT NO., PARTIAL PAYMENT NO., PROJECT, REQUISITION NO. and LOCATION.

Final payment

Form ARS-372 example filled out, final payment

FINAL PAYMENT has its own box.

For period beginning and ending

Form ARS-372 example filled out, for period beginning and ending

Fill in FOR PERIOD BEGINNING and ENDING.

Original contract, change orders and value of work completed

Form ARS-372 example filled out, original contract, change orders and value of work completed

Enter the Amount of original contract in Box 1 and the Change orders and/or amendments in Box 2; Box 3 is the Total adjusted contract prices.

Enter the Value of work completed to end of period in Box 4 and the Value of material stored at the site (Itemize below) in Box 5; Box 6 is the Total value of work completed and stored material (Line 4 plus Line 5).

Retainage and net amount due contractor

Form ARS-372 example filled out, retainage and net amount due contractor

Box 7 is Less % retainage.

Box 8 is the Total due contractor thru end of this period; Box 9 is Less previous requests; Box 10 is the Net amount due contractor this payment.

Material stored at the site

Form ARS-372 example filled out, material stored at the site

Under MATERIAL STORED AT THE SITE (See Item 5 above), enter a Description and Value for each item.

Contractor's progress payment certification and signatures

Form ARS-372 example filled out, contractor's progress payment certification and signatures

By signing you certify, to the best of your knowledge and belief, that -

The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and this certification is not to be construed as final acceptance of a subcontractor's performance.

Sign on SIGNATURE OF CONTRACTOR'S AUTHORIZED REPRESENTATIVE and enter the DATE SIGNED.

RECOMMENDED FOR PAYMENT has a DATE SIGNED.

More rules for Form ARS-372

The previous edition is not usable.

Sources

[1] Form ARS-372 (06/2011), Contractor's Request for Payment Transmittal, USDA Agricultural Research Service (the Official source link on this page).

Please rate Ars 372

1 Votes
If you believe this page is infringing on your copyright, please familiarize yourself with and follow our DMCA notice and takedown process - click here to proceed .