Understanding the ins and outs of the WH-40 form is crucial for anyone involved in public works projects in Oregon. Essentially, this form plays a pivotal role in the financial close-out process of these projects, helping ensure that all monetary transactions related to prevailing wage rates are settled correctly. Managed by the Bureau of Labor and Industries located in Portland, Oregon, this form must be completed by public agencies after the completion of a public works project. It is a mandatory step that allows for the reconciliation of fees based on the final contract price, which may have changed due to various adjustments or change orders during the project's lifespan. Essentially, the WH-40 form facilitates the accurate calculation of the prevailing wage rate fee, taking into account any past payments and factoring in all revisions to the original contract price. Public agencies are required to submit this form no less than 30 days after the final progress payment to the contractor, including supporting documentation for the final contract price. This meticulous process ensures transparency and compliance with regulations, highlighting the significance of this document in maintaining the integrity of public works administration and labor compensation.
Question | Answer |
---|---|
Form Name | Form Wh 40 |
Form Length | 1 pages |
Fillable? | No |
Fillable fields | 0 |
Avg. time to fill out | 15 sec |
Other names | CCB, PREVAILING, RECONCILED, substantiating |
CONTRACT FEE SECTION
PREVAILING WAGE RATE UNIT
BUREAU OF LABOR AND INDUSTRIES
800 N.E. OREGON ST., #1045
PORTLAND, OR
PHONE: (971)
FAX: (971)
For Office Use Only:
Project DB #:
PUBLIC WORKS FEE ADJUSTMENT FORM
THIS FORM TO BE USED FOR RECONCILIATION OF FEES UPON COMPLETION OF
PUBLIC WORKS PROJECTS
(As required by ORS 279C.825 and OAR
PUBLIC AGENCIES: Complete and mail this form to BOLI at the above address after completion of the public work project and not less than 30 days after the final progress payment is made to the contractor. Public agencies are required to determine the final contract price, including all change orders or other adjustments to the original contract price, and to calculate the adjusted prevailing wage rate fee based on the revised contract price. Documentation must be included to support the final contract price. Documentation of the final contract price may consist of change orders or other contract documents substantiating the amount of the contract. The prevailing wage rate fee of
PAID, AND REFUNDS WILL NOT BE MADE, FOR RECONCILED AMOUNTS OF LESS THAN $100.00.
PUBLIC AGENCY: |
|
|
|
|
|
|
|
|
|
|
AGENCY #: |
|
|
||||||||||||
AGENCY CONTACT PERSON: |
|
|
|
|
|
|
|
|
|
PHONE:( |
) |
||||||||||||||
MAILING ADDRESS: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||
PROJECT NAME: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||
CONTRACT NAME (if part of larger project): |
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||
PROJECT NUMBER: |
|
PROJECT LOCATION: |
|
|
|
|
|
|
|
||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||
CONTRACTOR/BUSINESS NAME (DBA): |
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||
CONTRACTOR CCB#: |
|
|
|
|
|
|
DATE AWARDED: |
|
|
||||||||||||||||
FINAL CONTRACT/PROJECT AMOUNT: |
|
|
|
|
FINAL FEE DUE: |
|
|||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
||||||||||||||||
(Include all change orders and adjustments to the contract price) |
(Final Contract amount X |
||||||||||||||||||||||||
.001) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ORIGINAL CONTRACT AMOUNT: |
|
|
|
|
|
|
|
INITIAL FEE PAID: |
|
||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(Original Contract amount X .001) |
|||||||
TOTAL ADJUSTMENT: |
|
|
|
|
|
|
|
|
BALANCE DUE*: |
|
|
||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
or |
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REFUND DUE*: |
|
|
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*Final contract fee less initial fee paid |
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||
|
Sample Calculation: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||
|
Final Contract Amount: |
$ 400,000.00 |
Final Fee Due: |
$ 400.00 |
|
|
|
||||||||||||||||||
|
Original Contract Amount: |
- 300,000.00 |
Initial Fee Paid: |
- 300.00 |
|
|
|
||||||||||||||||||
|
Total Adjustment: |
$ 100,000.00 |
Additional Amount Due: |
$ 100.00 |
|
|
|
||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(Please duplicate this form for future use)