How to Fill Out Form 1190

Form 1190 at a glance

What it is: Form 1190 is the Certification of Compliance with Subdivision and Shoreland Zoning Requirements.

Where and when to file: Return the certification to Central Maine Power Company, 162 Canco Road, Portland, ME 04103, CMP Fax 207-629-4752, or e-mail: Lineclerknewservice@cmpco.com.

A filled-in Form 1190 example: a customer asks the town for the certification

Form 1190 example filled out, example: a customer asks the town for the certification
Dana Sample, a customer, asks the town to sign Form 1190. The Code Enforcement Officer signs and dates it, and the Notification field holds the eight digits after the printed 1 0 3. The picture shows the filled form, and none of its entries is real.

How to fill out Form 1190, box by box

Notification and the customer

Form 1190 example filled out, notification and the customer

Provide a notification number on the form. The Notification line prints 1 0 3 and is for 11 digits.

Enter the Name of Customer.

Enter the Mailing address and the Daytime Telephone.

Service address

Form 1190 example filled out, service address

The customer identified in Name of Customer has requested utility services at the service address. Provide the service Location on that line: insert street and town, map and lot, or other identification of the location of installation.

Certification by Municipal Official

Form 1190 example filled out, certification by Municipal Official

In the Certification by Municipal Official, the official certifies that all local permits and/or approvals, if any, required under Title 30-A M.R.S.A. Chapter 187 (the subdivision and land use statute) have been issued by the appropriate municipal official(s) and are current.

The official also certifies that all local permits, if any, required under Title 38 M.R.S.A. Chapter 3 (the shoreland zoning and water protection statute) have been issued by the appropriate municipal official(s) and are current.

A municipal official signs the form as noted on the form: the official fills in the Date, signs on the Signature line, prints the name beneath the signature and enters the Official Title.

More rules for Form 1190

Maine statutes, Title 30-A M.R.S.A. §4406(3) and Title 38 M.R.S.A. §444, require utilities to obtain the certification from municipalities prior to installing service, except as stated on the form. You request that an appropriate municipal official (usually the Planning Board or Code Enforcement Officer) provide the certification so that the applicant can get utility service.

Common questions about Form 1190

Where do I file it?

Return the certification to Central Maine Power Company, 162 Canco Road, Portland, ME 04103, CMP Fax 207-629-4752, or e-mail: Lineclerknewservice@cmpco.com.

Sources

[1] Form 1190 (Rev 11/2018), Central Maine Power Company (the Official source link on this page).

Cmp 1190 Form PDF Details

This certification document plays a crucial role in ensuring compliance with subdivision and shoreland zoning requirements in Maine. A qualified municipal official must complete it to confirm that all local permits and approvals required by Title 30-A M.R.S.A. Chapter 187, relating to subdivision and land use regulation, and Title 38 M.R.S.A. Chapter 3, concerning shoreland zoning and water resource protection, have been duly obtained and remain current.

This document is a required prerequisite for any individual or entity applying for new utility services at a location subject to these regulations. Central Maine Power Company (CMP) requires the certification before provisioning new electric service, ensuring installations comply with state and local regulatory frameworks. The form requires the applicant's legal name, mailing address, telephone number, and a CMP-issued notification number, along with precise identification of the installation address and property location.

Who needs this certification: Property owners, developers, and contractors in Maine requesting new electric utility service connections must obtain this certification from their local municipality. This requirement applies to locations within designated subdivision zones or shoreland areas governed by municipal land-use ordinances. Without a signed certification, Central Maine Power will not process the service connection request.

What permits must be current: All permits issued under Title 30-A M.R.S.A. Chapter 187 (subdivision approvals and local land use) and any applicable shoreland management permits under Title 38 M.R.S.A. Chapter 3 must be active and current at the time of certification. Permits that are expired, conditionally approved, or still under review are not acceptable. The municipal official signing the certification is personally attesting that all required approvals are in good standing.

How the certification works: The property owner or contractor requests the certification from the appropriate municipal office, such as the planning board, code enforcement office, or town clerk, depending on local government structure. The municipal official reviews the permit status for the property and, if all approvals are current, signs and dates the certification. The completed document is then submitted to CMP before any service request can be processed.

Submission options: Central Maine Power accepts this certification by mail to their Augusta, Maine office, by fax, or by email. This flexibility allows applicants to submit using the most convenient method. After CMP receives the certification, the company verifies it before moving forward with the service connection request. Delays in submitting the certification can slow down the overall timeline for receiving new electric service.

For other utility-related documents, you may also need to complete an application for electric service to formally request your new connection from CMP. See our utility bill template for additional utility-related documents available at FormsPal.

QuestionAnswer
Form NameCmp 1190 Form
Form Length1 page
Fillable?Yes
Fillable fields9
Avg. time to fill out15 sec
Other namesmaine 1190 form, cmp form online, cmp 1190, cmp 1190 form