Nyc Form Tr2 PDF Details

In the bustling urban landscape of New York City, ensuring the integrity and safety of construction projects is paramount. The TR2 form serves as a critical tool in this ongoing effort, focusing on the documentation of concrete sampling and testing. A requirement for all relevant applications, this comprehensive document details essential information spanning from location specifics to the identification of responsibilities by licensed concrete testing laboratories. It necessitates the input of details such as house numbers, street names, and borough locations, as well as exhaustive information about the testing lab including the director's name, business address, and contact information. Beyond mere data collection, the form also requires certifications from various stakeholders, including the laboratory director, building owner, and design applicant, all affirming adherence to New York City's construction codes and the accurate reporting of test results prior to permit issuance and again prior to sign-off. Each section meticulously outlines the responsibilities and acknowledgements necessary to uphold standards of safety and compliance, echoing the city's commitment to maintaining rigorous quality control in construction practices. By mandating detailed reporting and accountability, the TR2 form plays a pivotal role in the city's broader regulatory ecosystem, safeguarding the structural integrity of its built environment.

QuestionAnswer
Form NameNyc Form Tr2
Form Length4 pages
Fillable?Yes
Fillable fields322
Avg. time to fill out1 min
Other namestr2 tr2 fillable form

How to Fill Out Form TR2

Form TR2 at a glance

What it is: TR2: Technical Report Concrete Sampling and Testing, filed prior to permit issuance to identify responsibilities and prior to sign-off to certify completion of testing and sampling of concrete.⁠[2]

Where and when to file: Pages 1 and 2, which include section 1 - section 5, must be completed and submitted prior to permit.⁠[2]

A filled-in Form TR2 example: a lab director files before the permit

Form TR2 example filled out, example: a lab director files before the permit
A concrete lab director files a TR2 before the permit. Pages 1 and 2, sections 1 to 5, are filled; sections 6 to 9 wait for sign-off. The picture shows page 1 of the form, and all its values are invented. The director is a P.E., so P.E. is chosen. No earlier director was designated, so Change of Applicant stays empty. The design applicant ticks the box in Design Applicant's Statement and Signature. Nothing goes in Test Report because it is required prior to sign-off. Nothing goes in Licensed Concrete Testing Laboratory's Certification of Completion because it is required prior to sign-off. Nothing goes in Design Applicant's Statements and Signatures because it is required prior to sign-off. Nothing goes in Concrete Producer's Statement and Signature because it is required prior to sign-off.

How to fill out Form TR2, box by box

Location Information

Form TR2 example filled out, location Information

1 Location Information is Required for all applications. Provide the borough, block, lot, Building Identification Number (BIN), community board, house number, and street name of the location for which testing is being performed.

Indicate specific areas represented in “Work on Floors”, such as building names, floor numbers, etc. Next is 2 Licensed Concrete Testing Lab Information.⁠[2]

Licensed Concrete Testing Lab Information

Form TR2 example filled out, licensed Concrete Testing Lab Information

2 Licensed Concrete Testing Lab Information is Required for all applications. Provide the last name, first name, and middle initial, business name, telephone number, address, and fax number of the director of the licensed concrete testing lab.

Provide the licensed concrete testing lab's license number and the licensed concrete testing lab director's license number.⁠[2]

Identification of Responsibilities and Change of Applicant

Form TR2 example filled out, identification of Responsibilities and Change of Applicant

3 Licensed Concrete Testing Laboratory's Identification of Responsibilities is Required prior to Permit. Prior to permit, the director of the licensed concrete laboratory must provide his/her name, sign and date the report, and place his/her seal in the space provided identifying responsibility of conducting the testing in accordance with BC 1905.6 and BC 1704.1.

By signing you certify that you are the director of the licensed concrete testing laboratory accepting responsibility for conducting the testing in accordance with BC 1905.6 and BC 1704.1.

By signing you further certify that you have read the applicable sections of the New York City Construction Codes in connection with the testing of concrete and licensed concrete testing laboratories as well as 1 RCNY §5-02 and 1 RCNY §101-07(c)(6), which specifies the qualifications and duties required of a licensed concrete testing laboratory and that this licensed testing laboratory meets those qualifications for the work which you take responsibility.

By signing you agree that both you and the licensed concrete testing laboratory will comply with all provisions of the New York City Construction Codes as well as 1 RCNY §5-02 and 1 RCNY §101-07(c)(6).

By signing you certify that you are aware of the additional sanctions imposed on false filings by §28-211.1.2 of the Administrative Code.

Change of Applicant: only a newly designated individual responsible for the testing marks one of these two boxes. First box: None of the tests indicated herein have been performed to date by the previously designated individual. Second box: Some of the tests indicated herein have been performed by the previously designated individual, as indicated in the attached report.

Enter Name (please print). Apply seal, then sign and date over seal.⁠[2]

Design Applicant's Statement and Signature

Form TR2 example filled out, design Applicant's Statement and Signature

4 Design Applicant's Statement and Signature P.E./R.A. is Required prior to Permit. Prior to permit, the design applicant must provide his/her name, sign and date the report, and place his/her seal in the space provided certifying the licensed concrete lab is acceptable as per BC 1704.1.

By checking the box you certify that the licensed concrete testing laboratory specified in section 2 above and engaged by the owner to perform tests on the work at the location specified in section 1 above is acceptable. (BC 1704.1)

Write Name (please print), then apply the P.E. / R.A. Seal and sign and date over it.⁠[2]

Building Owner's Statement and Signature

Form TR2 example filled out, building Owner's Statement and Signature

5 Building Owner's Statement and Signature is Required prior to Permit. The building owner must provide his/her name, sign and date the report certifying he/she employed the licensed concrete testing lab as per BC 1704.1.

By signing you certify that you have employed the licensed concrete testing laboratory specified in section 2 above in accordance with BC 1704.1.

Write Name (print) and Title, then sign and date. STOP HERE PRIOR TO PERMIT.⁠[2]

Test Report

6 Test Report is Required prior to Sign-off. Attach Original Lab Test Reports. Completed test reports must be attached when submitting the TR2 prior to sign-off.

In 6 Test Report, the licensed concrete testing laboratory is required to fill in the specified concrete strength (psi) as Specified Concrete Str. (f' c) in PSI, the specified test age in days as Required Test Age (days), the test report number from original lab test report, the date of concrete placement, the Cylinder ID, the field test data - slump (inches), air content (%), Temperature (degrees F), unit weight (pcf), the location of concrete placement represented by test data, the total placement volume in cubic yards, and the compressive strength of the cylinder. Original Lab reports must be attached.

Use supplemental pages as needed for the test report. Submit as many pages as needed to provide all test results.

The licensed concrete testing lab director shall sign and seal every page.

Write the Licensed Concrete Lab Director Name (please print), then apply the seal, then sign the Signature line and date over the seal.⁠[2]

Licensed Concrete Testing Laboratory's Certification of Completion

7 Licensed Concrete Testing Laboratory's Certification of Completion is Required prior to Sign-off. Prior to sign-off, the director of the licensed concrete laboratory must provide his/her name, sign and date the report, and place his/her seal in the space provided certifying completion of the testing specified in the report.

By signing you certify that you have completed the testing specified herein and that the results reported in section 6 of this form are true and accurate in accordance with §28-406.3.2.

Withdrawal of Applicant: mark this box only if you are withdrawing. I am withdrawing responsibility for conducting the tests indicated herein and herewith submit the results or status of the work performed to date.

Enter Name (please print) and Signature Date, and apply seal, then sign and date over seal.⁠[2]

Design Applicant's Statements and Signatures

8 Design Applicant's Statements and Signatures is Required prior to Sign-off. P.E./R.A. responsible for plans, choose one and sign/seal. Prior to sign-off, the design applicant must provide his/her name, sign and date the report, and place his/her seal in the space provided certifying he/she has reviewed the test results and found them to be in compliance with the approved construction documents.

By signing you certify you have reviewed the test results reported by the licensed concrete testing lab in section 6 above and found them to be in compliance with the approved construction documents, or in compliance except as noted in the attached report (BC 1905.6). Note: design applicant's signed and sealed report must be attached to this document.

Fill Name (please print) and apply the P.E. / R.A. Seal, then sign and date over seal.⁠[2]

Concrete Producer's Statement and Signature

9 Concrete Producer's Statement and Signature is Required prior to Sign-off. Must be filled out by Owner of Production Facility. Prior to sign-off, the concrete producer must provide his/her name, sign and date the report certifying the concrete mix delivered is as per the design mix on the TR3 that has been submitted.

By signing you certify that the test results reported in section 6 above were reported to you, and you further certify that the concrete delivered is in accordance with the design mix(es) specified on the TR3 submitted for the work specified in section 1 above.

Write Name (print), Title, Business Name, Business Telephone, Business Address, Business Fax:, City, State and Zip, then sign and date and write the NRMCA/CIB Expiration Date (BC 1905.8.2).⁠[2]

More rules for Form TR2

Must be typewritten.

As a reminder, additional TR2 reports should be submitted as needed.⁠[2]

Common questions about Form TR2

Is there a deadline?

Pages 1 and 2, which include section 1 - section 5, must be completed and submitted prior to permit. Prior to Sign-off: Pages 1 and 2 should be printed from BISWEB and the rest of the report (sections 6 - section 9) should be completed and submitted prior to sign-off.⁠[2]

Is there a penalty?

Falsification of any statement is a misdemeanor and is punishable by a fine or imprisonment, or both.

Sources

[1] Form TR2 (12/14), Technical Report: Concrete Sampling and Testing, New York City Department of Buildings (the Official source link on this page).

[2] TR2 Instructions (11/20), New York City Department of Buildings.