Form 408C PDF Details

COMcheck (Recommended): A COMcheck compliance certificate demonstrating the project's compliance with IECC-2021 or ASHRAE 90.1-2019 is attached to this statement.

Submit: with every application to construct or alter a building, other than a residential building with four or fewer stories above grade plane.

Residential: a Residential Compliance Statement must be filed for a residential building with up to four stories above grade plane.

Permits: no form is required with permit applications for temporary structures, communications equipment, construction equipment, or electrical-only permits.

Signature block: Date, Professional Seal, Signature, Printed Name and Illinois License Number.

QuestionAnswer
Form NameForm 408C
Form Length1 page
Fillable?Yes
Fillable fields23
Avg. time to fill out4 min
Editionrev. 10/31/2022
Issuing agencyChicago Department of Buildings
Matches the agency's fileYes, checked October 4, 2026
Other namesForm 408C, 408C, Commercial Compliance Statement, Chicago energy transformation code compliance statement, Chicago Department of Buildings Form 408C
Official sourceForm 408C (10/31/2022), Chicago Department of Buildings

How to Fill Out Form 408C

Form 408C at a glance

What it is: Form 408C rev. 10/31/2022 is the 2022 Chicago Energy Transformation Code Commercial Compliance Statement of the Department of Buildings.

Where to get it: Form 408C rev. 10/31/2022 Fillable PDF available at www.chicago.gov/permit.

An Illinois-licensed architect or engineer must complete this form and submit it with every application to construct or alter a building, other than a residential building with four or fewer stories "above grade plane". A Residential Compliance Statement must be filed for a residential building with up to four stories "above grade plane". If a mixed-occupancy building contains both a non-residential occupancy and a residential occupancy up to four stories "above grade plane", both forms must be filed. No form is required with permit applications for temporary structures, communications equipment, construction equipment, or electrical-only permits.

A filled-in Form 408C example: an architect certifies a new office building

Form 408C example filled out, example: an architect certifies a new office building
An Illinois-licensed architect files a Form 408C for a six-story office building. The project is in compliance and uses COMcheck. The picture shows the form, and none of its entries is real. Exempt is left blank because the project is not exempt. Nothing goes in the rest of Compliance Method because COMcheck is the method.

How to fill out Form 408C, box by box

Project Address and Permit Application Number

Form 408C example filled out, project Address and Permit Application Number

Under Application Details, enter the Project Address and the Permit Application Number.

In compliance or Exempt from the commerical requirements

Form 408C example filled out, in compliance or Exempt from the commerical requirements

Select In compliance with the commerical requirements of the 2022 Chicago Energy Transformation Code, "as detailed below", when all work shown in the construction documents for this application is in compliance.

Select Exempt from the commerical requirements of the 2022 Chicago Energy Transformation Code as: (select one) the reconstruction or renewal of any part of an existing building for its maintenance or to correct damage (No alterations or additions). Or the alteration, relocation, or change of occupancy of a historic building, and the report required by Section C501.6 is attached to this statement.

Date, Professional Seal, Signature, Printed Name and Illinois License Number

Form 408C example filled out, date, Professional Seal, Signature, Printed Name and Illinois License Number

The construction documents submitted with this application comply with the specific requirements of the Chicago Energy Transformation Code and the general requirements of the Chicago Construction Codes Administrative Provisions (Title 14A).

You have notified the permit applicant of all post-construction testing and commissioning requirements of the Chicago Energy Transformation Code which are applicable to the project based upon the scope of work and the compliance method "identified below".

Enter the Date, Professional Seal, Signature, Printed Name and Illinois License Number.

Compliance Method

Form 408C example filled out, compliance Method

COMcheck (Recommended): a COMcheck compliance certificate demonstrating the project's compliance with IECC-2021 or ASHRAE 90.1-2019 is attached to this statement. Complete and accurate information about the project was entered into COMcheck.

Visit www.energycodes.gov/comcheck for more information.

IECC Prescriptive Path: a report or narrative substantiating how the project complies with the prescriptive requirements of the Energy Transformation Code, including Sections C402, C403, C404 and C405 is attached to this statement. The project meets Section C406 by: (select one) more efficient HVAC performance, reduced lighting power density system, enhanced lighting controls, on-site supply of renewable energy, dedicated outdoor air system for HVAC, high-efficiency service water heating, enhanced envelope performance, reduced air infiltration, exception: previously occupied tenant space

IECC Total Building Performance Method: the project complies with Section C407 and a compliance report meeting the requirements of Section C407.3.1 is attached to this statement. An explanation of any error or warning message appearing in the simulation tool output is also attached.

ASHRAE 90.1 Prescriptive Path: the project complies with Sections 5, 6, 7, 8, 9 and 10 of ASHRAE 90.1-2019, "as described below", and complete compliance forms from the 2019 edition of the 90.1 User's Manual or equivalent documentation is attached to this statement: (select one in each column) 5.5 prescriptive building envelope, 5.6 building envelope trade-off, 6.3 simplified HVAC, 6.5 HVAC prescriptive path, 6.6 HVAC alternative compliance path, 9.5 lighting - building area method, 9.6 lighting - space-by-space method

ASHRAE 90.1 Energy Cost Budget: the project complies with Section 11 of ASHRAE 90.1-2019 and documentation complying with Section 11.7 is attached to this statement.

ASHRAE 90.1 Performance Rating Method: the project complies with Normative Appendix G of ASHRAE 90.1-2019, and a simulated performance report, complying with Section G1.3 is attached to this statement.

Phius Certification: the project will be certified under the 2021 Phius Passive Building Standard Certification Guidebook (v. 3.1) and evidence of certification will be filed with the Department of Buildings within 180 days of project completion.

National Green Building Standard (NGBS) Certification: the project will be certified at the Gold or Emerald level under the 2020 National Green Building Standard and evidence of certification will be filed with the Department of Buildings within 180 days of project completion.

More rules for Form 408C

Fields and sections marked with a red star are required.

Sources

[1] Form 408C (rev. 10/31/2022), 2022 Chicago Energy Transformation Code Commercial Compliance Statement, Chicago Department of Buildings (the Official source link on this page).