ENG Form 4025-R at a glance
What it is: ENG Form 4025-R is the Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer's Certificates of Compliance.
Who signs: Section I will be initiated by the Contractor in the required number of copies.
A filled-in ENG Form 4025-R example: a contractor sends one product submittal

How to fill out ENG Form 4025-R, box by box
The transmittal and the contract

DATE TRANSMITTAL NO. TO: FROM: CONTRACT NO. CHECK ONE: THIS IS A NEW TRANSMITTAL, THIS IS A RESUBMITTAL OF.
Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section.
If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.
Project and specification section

Enter the PROJECT TITLE AND LOCATION and the SPECIFICATION SEC. NO. (Cover only one section with each transmittal).
Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.
Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.
The items, columns a to i

a. ITEM NO. (See Note 3) c. SUBMITTAL TYPE CODE (See Note 8) g. CONTRACTOR REVIEW CODE i. USACE ACTION CODE (Note 9)
The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.
b. DESCRIPTION OF SUBMITTAL ITEM (Type size, model number/etc.)
When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.
Submittal types are the following: SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout
d. NO. OF COPIES e. SPEC. PARA. NO. f. DRAWING SHEET NO. under CONTRACT DOCUMENT REFERENCE
For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I.
The U.S. Army Corps of Engineers approving authority will assign Submittal Action Codes in column i of Section I.
The Submittal Action Codes are: A -- Approved as submitted. B -- Approved, except as noted on drawings. Resubmission not required. C -- Approved, except as noted on drawings. Refer to attached comments. Resubmission required. D -- Will be returned by separate correspondence. E -- Disapproved. Refer to attached comments.
F -- Receipt acknowledged. X -- Receipt acknowledged, does not comply with contract requirements, as noted.
G -- Other action required (Specify) K -- Government concurs with intermediate design. (For D-B contracts) R -- Design submittal is acceptable for release for construction. (For D-B contracts)
Approval of items does not relieve the contractor from complying with all the requirements of the contract.
Variation and Remarks
Contractor certification and signature
More rules for ENG Form 4025-R
ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.
For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.
Sources
[1] ENG Form 4025-R (MAR 2012), U.S. Army Corps of Engineers (the Official source link on this page).