How to Fill Out ENG Form 4025-R

ENG Form 4025-R at a glance

What it is: ENG Form 4025-R is the Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer's Certificates of Compliance.

Who signs: Section I will be initiated by the Contractor in the required number of copies.

A filled-in ENG Form 4025-R example: a contractor sends one product submittal

ENG Form 4025-R example filled out, example: a contractor sends one product submittal
Sam Example, a contractor, submits ENG Form 4025-R for one product item. It is a new transmittal of product data from one specification section, with no variation. The picture shows the contractor's part, and every value in it is made up. The Resubmittal of box and its number stay empty in The transmittal and the contract because the transmittal is new. Only the DA box is ticked in This transmittal is for, so FIO, GA, CR, DA/CR and DA/GA stay empty. Column h is left blank in Variation and Remarks because the data meet the contract requirements, and Remarks is left blank for the same reason. Column i and Section II, approval action are left blank because the approving authority completes them. The contractor assigns code A in column g.

How to fill out ENG Form 4025-R, box by box

The transmittal and the contract

ENG Form 4025-R example filled out, the transmittal and the contract

DATE TRANSMITTAL NO. TO: FROM: CONTRACT NO. CHECK ONE: THIS IS A NEW TRANSMITTAL, THIS IS A RESUBMITTAL OF.

Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section.

If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

Project and specification section

ENG Form 4025-R example filled out, project and specification section

Enter the PROJECT TITLE AND LOCATION and the SPECIFICATION SEC. NO. (Cover only one section with each transmittal).

Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

This transmittal is for

ENG Form 4025-R example filled out, this transmittal is for

THIS TRANSMITTAL IS FOR: (Check one) FIO, GA, DA, CR, DA/CR, DA/GA.

The items, columns a to i

ENG Form 4025-R example filled out, the items, columns a to i

a. ITEM NO. (See Note 3) c. SUBMITTAL TYPE CODE (See Note 8) g. CONTRACTOR REVIEW CODE i. USACE ACTION CODE (Note 9)

The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

b. DESCRIPTION OF SUBMITTAL ITEM (Type size, model number/etc.)

When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following: SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

d. NO. OF COPIES e. SPEC. PARA. NO. f. DRAWING SHEET NO. under CONTRACT DOCUMENT REFERENCE

For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I.

The U.S. Army Corps of Engineers approving authority will assign Submittal Action Codes in column i of Section I.

The Submittal Action Codes are: A -- Approved as submitted. B -- Approved, except as noted on drawings. Resubmission not required. C -- Approved, except as noted on drawings. Refer to attached comments. Resubmission required. D -- Will be returned by separate correspondence. E -- Disapproved. Refer to attached comments.

F -- Receipt acknowledged. X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify) K -- Government concurs with intermediate design. (For D-B contracts) R -- Design submittal is acceptable for release for construction. (For D-B contracts)

Approval of items does not relieve the contractor from complying with all the requirements of the contract.

Variation and Remarks

ENG Form 4025-R example filled out, variation and Remarks

h. VARIATION Enter "Y" if requesting a variation (See Note 6)

If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

Contractor certification and signature

ENG Form 4025-R example filled out, contractor certification and signature

The NAME OF CONTRACTOR and the SIGNATURE OF CONTRACTOR go with this certification: I certify that the submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

Section II, approval action

ENG Form 4025-R example filled out, section II, approval action

SECTION II - APPROVAL ACTION has NAME AND TITLE OF APPROVING AUTHORITY, SIGNATURE OF APPROVING AUTHORITY, DATE and ENCLOSURES RETURNED (List by item No.).

More rules for ENG Form 4025-R

ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

Sources

[1] ENG Form 4025-R (MAR 2012), U.S. Army Corps of Engineers (the Official source link on this page).

ENG Form 4025-R PDF Details

When managing a construction or engineering project, handling documentation effectively is crucial to ensure that all elements align with contractual and regulatory requirements. Among the variety of documents and forms utilized for these purposes, the Eng 4025 R form serves a pivotal role. This form, designated for the Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer's Certificates of Compliance, facilitates a structured and official means of communication between contractors and the approving authority, typically the U.S. Army Corps of Engineers. The form is meticulously designed to cover all necessary details for the submission and approval process, including items such as the project title and location, the specific items being submitted for approval, and the type of submission. Furthermore, it indicates whether the submission is new or a resubmission, the relevant contract documents, and any variations from the contract specifications that are being requested. Additionally, it incorporates a certification by the contractor that the items submitted have been thoroughly reviewed and conform to the project's specifications, except where variations are noted. This process is bolstered by the systematic approach outlined for the numbering of transmittals and the detailed instructions for indicating the type of submittal and the action codes that apply, ensuring that each submission is clearly understood and can be processed efficiently. Such meticulous detailing within the Eng 4025 R form underscores its significance in maintaining smooth operation and compliance throughout the lifecycle of a project.

QuestionAnswer
Form Name ENG Form 4025-R
Form Length 2 pages
Fillable? No
Fillable fields 0
Avg. time to fill out 30 sec
Other names usace submittal form, eng form 4025, eng 4025r, 4025