EJCDC C-620 Contractor's Application for Payment at a glance
What it is: EJCDC C-620 is the Contractor's Application for Payment.
Who signs: The Engineer recommends payment of the Line 8 amount or another amount (attach an explanation of the other amount), and signs and dates. The Owner approves payment of the Line 8 amount or another amount (attach an explanation of the other amount), and signs and dates. If applicable, the Funding Agency signs and dates Approved by Funding Agency.
A filled-in EJCDC C-620 Contractor's Application for Payment example: a contractor requests payment on page 1

How to fill out EJCDC C-620 Contractor's Application for Payment, box by box
Application No., Application Period, Owner, Contractor, Engineer

Enter the Contractor's Application for Payment No., the Application Period and the Application Date.
Enter the Owner in To (Owner), the Contractor in From (Contractor) and the Engineer in Via (Engineer).
Enter the Project and the Contract, then the Owner's Contract No., the Contractor's Project No. and the Engineer's Project No.
Approved Change Orders
Application For Payment, boxes 1 to 9

In box 1, enter the Original Contract Price.
In box 2, enter the Net change by Change Orders.
In box 3, enter the Current Contract Price (Line 1 ± 2).
In box 4, enter the Total Completed and Stored to Date (Column F on Progress Estimate).
In box 5, Retainage, enter the retainage on Work Completed in line a and the retainage on Stored Material in line b, then the Total Retainage (Line 5a + Line 5b) in line c.
In box 6, enter the Amount Eligible to Date (Line 4 - Line 5c).
In box 7, enter Less Previous Payments (Line 6 from prior Application).
In box 8, enter the Amount Due This Application.
In box 9, enter the Balance to Finish, Plus Retainage (Column G on Progress Estimate + Line 5 above).
Contractor's Certification and signatures

The undersigned Contractor certifies that to the best of its knowledge: (1) all previous progress payments received from Owner on account of Work done under the Contract have been applied on account to discharge Contractor's legitimate obligations incurred in connection with Work covered by prior Applications for Payment; (2) title of all Work, materials and equipment incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to Owner at time of payment free and clear of all Liens, security interests and encumbrances (except such as are covered by a Bond acceptable to Owner indemnifying Owner against any such Liens, security interest or encumbrances); and (3) all Work covered by this Application for Payment is in accordance with the Contract Documents and is not defective. The Contractor signs the By line.
If applicable, the Funding Agency signs and dates Approved by Funding Agency.
Progress Estimate by specification section

On the Progress Estimate, enter For (contract), Application Number, Application Period and Application Date.
For each specification section, enter the Specification Section No., Description and Scheduled Value.
Enter the Work Completed From Previous Application (C+D) and This Period, Materials Presently Stored (not in C or D), Total Completed and Stored to Date (C + D + E) and Balance to Finish (B - F).
Enter the Totals.
Estimated Quantity Installed by Bid Item
Sources
[1] EJCDC C-620 Contractor's Application for Payment (2007), Engineers Joint Contract Documents Committee (the Official source link on this page).



